Remove the old sink, toilet and bath
Remove cupboard
Take off the ceiling – to integrate new extractor fan, + install new spotlights
Plasterboards to be fitted to ceiling
Skim ceiling with multi-finish.
Remove wallpaper from walls
Old walls to be skimmed
Remove the floor and floor boards to allow fit of marine wood and be level with the corridor
Change doors of Cupboard over boiler
Fit marine wood and screw it to fit tiles
Fit tiles to floor and grouting
Fit tiles on walls and grouting
Tiles fitted around the bath
Tiles fitted around the toilet. – 1.50 height.
Fit new bath, sink and toilet and plug in with water.
Paint the bathroom – 3 layers.

Negative Review for Property Care on 9th Sep 2010
Amilton & his team worked hard, but the work was rushed at the end, and consequently there were parts not finished properly which subsequently had to be re-done. There is still a minor leak which needs to be fixed which no one has bothered to come back to me on.