How long should it take a plumber to install a new shower, toilet, basin and towel rail, given that the the old sanitary ware has been already stripped out and the new tiling and first fix plumbing already done?
If all water supplies and waste pipes where installed correctly- measured to right height/ position) then positioning and direct connecting with isolator valves, traps should not take more than few hours ( depending on previous pipes positioning accuracy). If You have vanity units for WHB & Toilet it also required extra time for alteration and positioning. In summary it should take from 4-6 hours if pre installation works has been done well .
The max time to install those appliances as a proper job and testing it should take 2-3 days .
HEMS
42 Reviews, 98% Positive
At most 4 days
If there is not much pipe work to do then it could be done in a day at a push but more two days would be a good amount time to install everything and get it all sealed up and good to go .
1 to 2 days you would expect providing every thing is first fixed correctly and in the right place
1 to 2 days if its just reinstating the white goods no tilling no flooring just instating and the shower vaulve pipe work there already
If everything is onsite ready to be installed along with the fixings, a day and a bit maximum.
Approx. 1.5-2 days to ensure a quality finish is achieved. M.A.D Home Improvement quote per job to ensure the job is completed to our high standards
I think two days should be enough unless the first fix was not done accurately and will require modifications that may be three days
Normally standard installation would be around 1-2 days depending on style of fixtures
Hi there. Personally I could not see it taking any longer than 2 days maximum to install and test everything if it is as you say and all the pipes and connections are in the right place
It can take 1/2days depending on the tiles and complexity of your chosen bathroom furniture
2-3 days because in some cases you need to allow the silicons to set and dry properly before work can be completed.
Without any problems usually between 5-7 days.