How long to allow for a bathroom refit?

Looking for some advice regarding how long to leave for a complete bathroom refit including some tiling and minor plumbing changes. Is a 3 days reasonable?

33 Answers

No, some time need 4 days for bathroom refit
23rd Nov 2015
Helpful Answer? Vote Up thumb up + 513
Post your job & get responses from local bathroom fitters. Read reviews before you decide to hire.
I'm looking for ...
Lillywhite Property Group LTD
13 Reviews, 92% Positive
I would allow 10 - 14 days.
23rd Feb 2016
Helpful Answer? Vote Up thumb up + 476
CM Prestige Heating & Plumbing Ltd
10 Reviews, 80% Positive
Dipends on waht has to be done.pipe change, waste change about a day for a bath only.
19th Nov 2015
Helpful Answer? Vote Up thumb up + 462
Beenrecommended
58 Reviews, 97% Positive
2-3 weeks depending on work required
31st Dec 2015
Helpful Answer? Vote Up thumb up + 441
London Central Gas
0 Reviews
Depends on what you want doing, how long is a piece of string, get a quote and see
1st Feb 2016
Helpful Answer? Vote Up thumb up + 438
COX PROPERTY & GARDEN SERVICES
4 Reviews, 100% Positive
5 to 8 days depending on what needs doing tiling etc
29th Dec 2015
Helpful Answer? Vote Up thumb up + 435
For a complete bathroom refit you will need 5 days to bee sure all is going fine.
22nd Nov 2015
Helpful Answer? Vote Up thumb up + 426
A&R Response
164 Reviews, 96% Positive
I would strongly suggest the time set a side for a complete bathroom refurbishment, depending on the size of bathroom. No less then two weeks.
You have to understand this is a room that will be used every day for water. It is so important that this area be left to dry out fully during refubishment. I.e tilling walls and floor.
3rd Jan 2016
Helpful Answer? Vote Up thumb up + 426
I would agree with the time frame you have put in your question for a bathroom refit depending on the size of the tiled area. Craig CLW plumbing. Pontefract
9th Mar 2016
Helpful Answer? Vote Up thumb up + 426
Bertoni Construction ltd
2 Reviews, 100% Positive
3-5 days
3rd Mar 2016
Helpful Answer? Vote Up thumb up + 419
bigoakbuilding & handyman services
8 Reviews, 75% Positive
A complete refit 1 - 2 weeks , but to change say a new bathroom suite takes a day , so if as you say minor changes 3 days sounds about right
11th Mar 2016
Helpful Answer? Vote Up thumb up + 413
Mike's Maintenance
1 Reviews, 100% Positive
Depends on the spec, type of fittings and size of tiles, amount of pipe work that needs changing, but remember you need to let the sealant dry before you use it. I would say 3 days basic 5 days major.
4th Apr 2016
Helpful Answer? Vote Up thumb up + 413
simon wall plumbing and tiling
2 Reviews, 100% Positive
A complete bathroom refit to me includes removing everything, bathroom suite, fixtures and fittings, floor and wall tiles - if they are present.
This will require more than 3 days. On average, most bathroom refits should take from 1 to 3 weeks, but even longer depending on the work required and the design of the re fit.
Problem that can be encountered which will add time to the install could be, rotten floorboards that need replacing. leak damage to the walls, which need to have the plaster chopped off and re rendered then skimmed, this can add quite a lot of days to an install, because if the room is to be tiled floor to ceiling, then the new render needs at least two weeks to be fully dry before it can be sealed and tiled!
The worst case would be to have lathe and plaster walls, typically found in older houses. As i have found on my experience, these walls begin to crumble over the years.making them unstable to mount fixtures on or to tile over.
With some of the modern large heavy tiles, lathe and plaster is not a suitable base to be fixing tiles to. I always remove this and start fresh with 12.5mm plasterboard.
29th Jan 2016
Helpful Answer? Vote Up thumb up + 412
homecare solutions
0 Reviews
the tiling is the thing that takes time if the some tiling is a bath slashback to ceiling the yes 3 days is plenty
3rd Jan 2016
Helpful Answer? Vote Up thumb up + 410
barticelsolution
2 Reviews, 100% Positive
6 day for a good job
12th Apr 2016
Helpful Answer? Vote Up thumb up + 408
John Powney plumbing& heating ltd
3 Reviews, 100% Positive
3 days could be ok if it is a full bathroom re fit it could be between 5 /7 days
20th Jun 2016
Helpful Answer? Vote Up thumb up + 407
GRCON Ltd
0 Reviews
For a complete bathroom refurbishment you need at least 5 working days.
7th Jan 2016
Helpful Answer? Vote Up thumb up + 400
V P G
0 Reviews
Hi,it depends on how much tiling is required and what alterations are needed to be made. I personally allow 5 to 10 days depending on size for a complete refit and fully tiled.
21st Dec 2015
Helpful Answer? Vote Up thumb up + 399
M.M Construction
8 Reviews, 88% Positive
three days should be plenty of time, as long as all materials and equipment are on site, for a bathroom of average size.
12th Jan 2016
Helpful Answer? Vote Up thumb up + 399
A.L Plumbing
1 Reviews, 100% Positive
Would be down to if tile need removing, is floor being tiled. If complete job we allow 3-4 days
18th Nov 2015
Helpful Answer? Vote Up thumb up + 397
2-3 weeks if tiling
2nd Dec 2015
Helpful Answer? Vote Up thumb up + 390
n d builders
23 Reviews, 96% Positive
we say a 3 to 5 days depending on how much tilling needs to be done etc but its hard to say with out seeing the job
26th Apr 2016
Helpful Answer? Vote Up thumb up + 390
MultiFM Limited
0 Reviews
Experience has taught me that you should always allow a week (5 days)to completely refurb an average bathroom properly. This will allow for any issues that may come up and also means the work will not be rushed an you will have a quality finish.
If the work is completed early you won't be disappointed but if there are any issues it shouldn't over run.
25th Dec 2015
Helpful Answer? Vote Up thumb up + 387
I would say that depending on weather the pipe work in the bathroom as got to be re directed and want as got to be fitted. Including how much tiling there is to be done i would say around a weeks work to complete this job
9th Dec 2015
Helpful Answer? Vote Up thumb up + 384
Js plumbing and heating
8 Reviews, 100% Positive
3 days usual time scale depending on tiler
12th May 2016
Helpful Answer? Vote Up thumb up + 382
SG Trades
60 Reviews, 100% Positive
Just a straight swap like for like without tiling 1.5 to 2 days.
For a full refurbishment 7 to 10 days depending on layout.
17th Mar 2019
Helpful Answer? Vote Up thumb up + 377
OSM Building Contractors
13 Reviews, 85% Positive
allow 1 day for 3-pce suite change and 1 day for minor tiling/plumbing alterations
5th Jul 2016
Helpful Answer? Vote Up thumb up + 377
gulfbuilder ltd
0 Reviews
No I think at least one week
21st Jan 2016
Helpful Answer? Vote Up thumb up + 375
Plumbing world
0 Reviews
Hello , yes it takes 3 or 4 days
15th Jan 2017
Helpful Answer? Vote Up thumb up + 356
if there is a comprehensive renovation of three days it is a realistic time for a complete renovation of a five-six days. Regards
5th Jan 2017
Helpful Answer? Vote Up thumb up + 347
Bathrooms
4 Reviews, 100% Positive
I would suggest from removal to complete installation at least 7 days for an average bathroom.
31st Jan 2017
Helpful Answer? Vote Up thumb up + 320
Royalflush Plumbing and Heating.
2 Reviews, 100% Positive
I would always allow between 3-5 days for a little bathroom 9am - 5pm and for a medium to large allowing 1-2 weeks again 9am -5pm full days you will find if they rush the tiling will be not as good as you would find taking time, tiling in a bathroom fully should be done in around 2-4days including bits of grouting for fixtures.
7th Mar 2017
Helpful Answer? Vote Up thumb up + 298
No
23rd Feb 2019
Helpful Answer? Vote Up thumb up + 202
Post your job & get responses from local bathroom fitters. Read reviews before you decide to hire.

I'm looking for ...

How it Works

step1
Read reviews before you decide to hire.
See how it works