Consumer Unit Swap + Extras


  • Electrical fitting
  • Melton Mowbray
  • Posted 11th Oct 2011

Install socket fronts on 3 new ring mains that have been ran (approx 25 double sockets)

Connect switches and connect light fittings up on a lighting circuit (7 switches 7 light fittings all cable has been ran and fittings attached).

Connect above circuits into new CU, move, inspect and test current lighting circuit, cooker circuit, kitchen radial circuit and boiler circuit over to new CU (provided) and connect tails.

Check earth bonding and:
Issue BS7671 Cert, Building Reg compliance cert and notify building control.

All cable has been run and CU/Sockets/Light fittings provided so it is essentially labour.
Positive Review for Power Sonic Limited on 10th Nov 2011
Power Sonic Limited, carried out a CU change and 2nd Fix in our property. He did a good job, was a hard worker and trustworthy and nothing was to much trouble. He would always answer your calls and e-mails promptly and turned up when he said he would. I found his prices fair and would definitely use and recommend his services again - A good honest sparky!