Beginning your extension.

About to purchase a property that has planning permission for a double story extension. The permission runs out next December but it says "The development hereby permitted shall be begun within three years of the date of this permission." I don't have the funds to complete the whole project straight away so I wanted to know when they say begin, what's the littlest amount of work you can do to show it has begun if that makes sense. Seems a waste of time getting plans drawn up again and all that.

11 Answers

Get the footing done and you will be perfectly fine
26th Sep 2022
Helpful Answer? Vote Up thumb up + 51
Post your job & get responses from local extension builders. Read reviews before you decide to hire.
I'm looking for ...
C&B BUILDERS
27 Reviews, 100% Positive
I would recommend trying to complete the shell but i think would get away with concreting the footing building footing and pouring the floor .
1st Nov 2022
Helpful Answer? Vote Up thumb up + 50
Quality Interior Solutions,Ltd
18 Reviews, 100% Positive
Contact your local council for that
2nd Oct 2022
Helpful Answer? Vote Up thumb up + 44
Pickup homes
0 Reviews
Excavation of foundations and filling with concrete should be sufficient
It should say somewhere in the conditions
3rd Jan 2023
Helpful Answer? Vote Up thumb up + 42
Simply Home Designs
2 Reviews, 100% Positive
As long as you can show you have started they should have no problem with can taking a little longer to build the extension dig some of the footings that will be ok
6th Feb 2023
Helpful Answer? Vote Up thumb up + 42
Olno Brickwork
0 Reviews
This can be extended if you ring your local council it would cost a couple of hundred pound I believe
22nd Feb 2023
Helpful Answer? Vote Up thumb up + 42
The littlest amount is to start ordering material for the work ahead also any works of construction, demolition, digging foundations, laying out or constructing a road and a material change in the use of the land.
14th Jan 2023
Helpful Answer? Vote Up thumb up + 41
An builders
0 Reviews
Marking out with wooden steaks in ground for building footprint
28th Jan 2023
Helpful Answer? Vote Up thumb up + 41
You have to get it up to dpc level.
6th Jun 2023
Helpful Answer? Vote Up thumb up + 37
LB Brickwork
0 Reviews
If you just dig it and pour the concrete foundation that will be classed as staring it
13th Jun 2023
Helpful Answer? Vote Up thumb up + 36
Bring it up to foundations/dpc hight
20th Dec 2023
Helpful Answer? Vote Up thumb up + 16